Half of the city is without hot water and the construction company that is doing our work was called by the city administration to repair it. We have now gone four days without seeing any more progress on the hole.
As of noon Friday,approximately 150 blocks have been thoroughly cleaned (they are used block -- old soviet military base blocks), thanks to the team from California. The Russian men have had to expand the fence almost twice the size to accommodate all of the block. About 90 percent of the blocks have been delivered, all of the pillow blocks have been delivered, and I believe all of the floor panels have been delivered.
In additon we have had three truckloads of sand and 20 bags of portland cement delivered. We still have not been told by the engineer what mixture he wants the mortar and we still lack a mixer, but we have a promise of one next week. Fighting the rain with prayer. Thanks for your encouragement and prayers.
Glad to be here. Bob & Robin